Disclaimer:
This topic has been thoroughly hashed out, but I'm mind-blocked on one component. I also know I'm over-thinking this.
Objective
On new hardware, create a test Domino Server to simulate a migration from one server to another and then simulate an in-place upgrade.
Current Environment (total: 3 servers)
-Windows Server 2008 R2 on each of the three servers
-2 Domino Enterprise Servers (8.5.3.FP6) are clustered together
-1 Domino Enterprise Server (9.0.1.) is for Traveler Server 9.0.1.
New Hardware
-Windows Server 2012 R2
-Test Server will focus on one of the two clustered servers
-Drives are mapped the same as current environment
Procedure (which I'm copying from other forums posts)
-Copy over the Domino Apps and Domino Data folders from current environment to test
-Copy over notes.ini from current to test
-Install Domino 8.5.3...